We have been advised by KCC that additional works are required to be undertaken on the new pedestrian crossing on Bellingham Way, prior to it being commissioned. This will involve overnight works as follows:-

5th June
Starting at 8pm until 3am – micro planing to all areas. This will be the noisiest night as the HFS install is by hand. The ops will be briefed about being quiet.

6th June
Installation HFS to 1 side 8pm to 3am

7th June
Installation HFS to 1 side 8pm to 3am